Interface Journal
The Journal of Wheel/Rail Interaction
Interface Journal
Navigation
  • Home
  • About Interface
  • Contact
  • Wheel Rail Seminars
  • Sponsorship
You are here: Home › Wheel/Rail Interaction › Norfolk Southern Embarks On a New Approach to Rail Defect Repair

Norfolk Southern Embarks On a New Approach to Rail Defect Repair

August 20, 2025 | Filed under: Wheel/Rail Interaction

by Jeff Tuzik

A plug rail insert mid-installation.

Internal rail flaws and defects are an unfortunate but unavoidable part of railroading. All railroads have them. All railroads have to repair them. Defect remediation, which involves cutting out the affected rail and replacing it with plug rail, is a necessary, but costly and time-consuming process; it’s a process with room for improvement. Norfolk Southern is currently testing a technology that aims to reduce the cost, track access time, and rail-mismatching drawbacks associated with the traditional defect repair process, and they’re already seeing results.

Norfolk Southern’s (NS) procedures for remediating internal rail defects are similar to any other class 1 railroad; due to FRA regulation and AREMA standards, this is a somewhat standardized process. But it’s a complex process. “To repair a defect in continuously-welded rail requires multiple work groups, multiple track blocks, and, on average, 21 feet of tested, matching plug rail,” Christopher Lorren, Engineer – Rail Health Management at Norfolk Southern, told delegates at the 2025 Wheel/Rail Interaction Heavy Haul conference.

Christopher Lorren, Engineer – Rail Health Management at Norfolk Southern. Photo: Mike Yuhas

On NS, when a defect is detected, either via ultrasonic testing or visual inspection, typically a crew tailing the inspection vehicle immediately flags the defect location and installs joint bars if necessitated by the defect type and severity, as per FRA Track Safety Standards CFR 213. The location and severity of the defect also dictates the level of protection, such as a slow order, the defect is given. This process typically occupies a 0.5 hour to 1 hour block of track time, Lorren said.

The next step is for a section gang to unfasten the adjacent rail, cut out the defect and install the plug rail, temporarily, via joint bars, and refasten the track. This typically requires an hour to 1.5-hour block of track time, he said.

The final step is to perform the welds. NS uses both thermite and flash-butt welding on their system, depending on the defect location and availability and logistics of welding trucks and crews (although flash-butt welding is preferred). Regardless of the weld type, these crews are tasked with removing the joint bars and welding the plug rail in place to complete the defect remediation process. This block of track occupancy can range from 1.5 hours to 4.5 hours depending on the complexity of the job, the type of weld, and the availability of track blocks, Lorren said.  

Kristopher Koski, President of ONE Rail Group. Photo: Mike Yuhas

In 2024 alone, NS tested more than 100,000 track miles, detecting over 7,500 defects in mainlines and sidings, Lorren said. Remediating these defects required a total of:

  • 157,000 feet of ultrasonically-tested, matching plug rail
  • 60,000 bolt holes and bolts
  • 30,000 joint bars
  • 22,500 saw cuts
  • 15,000 welds

That adds up to a lot of track time. “Our primary goals are to decrease our exposure and improve our efficiency,” Lorren said. “We want to be able to remediate a defect with a single crew, in a single block.”

Exposure and Efficiency

Sponsored Link: ONE Rail Group

Of course, a single crew is capable of removing, replacing, and welding a piece of rail, but there are logistical and technological constraints to consider. The average length of plug rail NS uses, at ≈21 ft, means that most jobs necessitate the use of a specialized grapple vehicle to transport and maneuver the plug and defect rails. “You lose a lot of time simply setting on [track] and setting off when you’re using these bigger hi-rail trucks,” said Kristopher Koski, President of ONE Rail Group. “If you can eliminate the need for a piece of equipment like that, you’re already more efficient.” The only way to eliminate the need for a grapple truck or overhead crane is to use a smaller section of plug rail. This would also have the add-on effect of reducing the labor and time associated with rail handling and with unfastening and refastening the track during the repair process, he said.   

Figure 1. Examples of thermite weld failures caused by finning at the base of the rail.

Ensuring the quality and consistency of welds is critical to the process; a failed weld is bad for both efficiency and exposure. A failed weld precipitates more track time, more material, more cost.

Thermite welds have a typical lifespan of ≈500 MGT, NS’ Lorren said. The most common mode of failure is “finning” at the base of the rail. Finning occurs when molten metals leaks out between the welding mold and the rail surface and fails to fully bond with the rail. This fin of material acts as a stress-riser and can initiate a fracture as the rail experiences bending and torsional stress over time. Figure 1 shows an example of a thermite weld failure due to finning at the base. “Thermite welding is a very manual process; it relies on a trained and skilled welder. It also relies on well-matched rail and plug rail,” he said.

Figure 2. Shear lip in a flash-butt weld (circled in red and shown in close-up on the right) caused by rail mismatch.

Electric flash-butt (EFB) welds are generally preferred to thermite welds. They typically have a lifespan of 1500 MGT, three times that of thermite welds, Koski said. “Flash-butt welding is the industry standard for long-term rail repair, but that doesn’t mean it can’t be improved.” Flash-butt welding removes much of the manual aspect from the equation by virtue of being a mechanized process, but these welds can fail, too. And when they do, the failure is often related to rail-mismatch, he said. In such cases, shear lip at the fillet radius between the rail head and web (see figure 2) acts as a stress riser and can initiate a fracture (see figure 3) under stress.

But matching plug rail to extant rail is not an easy task. “Railroads simply don’t store a lot of rail; those days are over,” Koski said. As a result, maintenance crews are rarely, if ever, able to find plug rail that perfectly matches the rail it’s replacing in terms of wear level and pattern.

Figure 3. A flash-butt weld failure caused by stress induced by shear lip.

The current AREMA standards allow for ±5 mm of mismatch between the rail and plug rail—figure 2, for example, shows a 4.7 mm mismatch (3 mm in the base and 1.7 mm in the head). “This [allowable mismatch] became the standard because railroads wanted to be able to weld 136 lb rail to 132 lb or 141 lb rail without having to put in a transition rail,” Koski said. The mismatch allowance makes it easier to find and install an acceptable plug rail, but the potential consequences of mismatch such as the inadvertent creation of stress risers and eventual weld failure must also be considered.

Rail Inserts

With the aim of reducing track occupancy time, increasing operational efficiency, and improving overall weld quality and consistency, NS has recently begun to trial a new defect remediation procedure that, for individual defects, uses small, proprietary machined Rail Inserts™ in place of traditional plug rail.

The inserts, which are in effect, very short sections of purpose-built plug rail, measure only 5 ft in length. They are manufactured from new rail, ultrasonically tested, and milled to match the extant rail to within ±2 mm of mismatch, Koski said. They are small enough that a grapple truck or overhead crane is not necessary to transport or handle them.

Figure 4. The Rail Insert Welding head, designed to weld short (down to 39 inches) lengths of purpose-built plug rail, in addition to traditional EFB welds.

The 5-foot inserts are, in fact, too small to weld with standard flash-butt equipment, which typically requires at least ≈12 ft of rail to ensure proper geometry and crown at the weld point, Koski said. The use of 5-foot inserts requires a welding head designed specifically for the task (see figure 4). One of the benefits of the design, and of welding such small pieces of plug rail, is that both welds fit within the envelope of the rail puller. This means that both welds are performed under compression; the crew doesn’t have to wait for the first weld to cool before performing the closure weld because the insert is never in tension during the process, he said. This saves time that can add up over the course of multiple welds in a shift. The welding head is also able to perform standard flash-butt welds, so welding crews don’t have to skip over standard joint removal/repair jobs.

Using these rail inserts, NS has, at the time of publication, repaired over 150 defects. And they’ve done so in one step, using one crew. Track occupancy time is down, too. A crew using the inserts can fully repair a defect in an hour and a half, NS’ Lorren said. “Conservatively, we’re saving one to two hours per defect when it comes to single-defect repair.” The five-person crew currently working with the inserts and insert welding head average 8.9 welds per shift—a figure that’s close to the output of a full flash-butt welding crew and significantly above that of equivalently-manned thermite crews, he said.   

A plug rail insert defect repair in service on Norfolk Southern.

“We’re at the first step of the process. We’re still testing and proving things out,” Koski said. As the program continues, NS and One Rail Group plan to expand the program to additional crews. There are also plans to expand rail insert inventory tracking such that a maintenance crew can query a database based on rail type and head loss to find the proper insert for the repair.  

As Koski said, these are early days for the program. The theory is sound and initial results are promising, but there isn’t much data to analyze yet. That will change in the coming months and years as these inserts accrue tonnage and the process is refined. But railroads are already taking notice; CSX has recently begun to trial this technology as well. It’s always interesting to find that in an area like defect repair that seems to be a “solved problem,” there is still room for innovation.  

Jeff Tuzik is Managing Editor of Interface Journal

This article is based on a presentation made at the 2025 Wheel/Rail Interaction Heavy Haul conference.

All images are courtesy of Norfolk Southern and ONE Rail Group except where otherwise noted.

Share this:

  • Click to share on X (Opens in new window) X
  • Click to share on Facebook (Opens in new window) Facebook

Related

Search by Category

Related Articles

  • Rail Seat Abrasion: In-Track Repair
    In relation to
    Measurement Systems
  • Mitigating Transverse Defects and Reducing Non-testable Areas: Grinding Strategies at CSX
    In relation to
    Measurement Systems
  • Digging Into Cause Codes for Track-Related Derailments
    In relation to
    Wheel/Rail Interaction
  • Assessing the Findings of a Derailment Investigation: Was the Right Cause Found?
    In relation to
    Brad Kerchof
  • Taking Stock of 30 Years of Wheel/Rail Interaction
    In relation to
    Wheel/Rail Interaction

Sponsors

ENSCO

© 2025 Interface Journal

 

Loading Comments...